Report showing who completed a task

Avatar

Level 4

Hi! I am looking for a way to create a task report to show who completed a task. I did try using the Last Updated By: Name column but this data was proving out to not be accurate for who actually completed the task. Thank you in advance.

7 Replies

Avatar

Level 9

Hei @Kiersten Kollins‚

Just a small question, are you looking also with in specific period, such as this month or also with respect to company.

Mvh

Kundan.

Avatar

Level 4

We would pull in all data since we implemented Workfront 2 years ago, but would use a prompt to target a timeframe for actual completion. Thanks!

Avatar

Level 10

Hi Kiersten - I have a note report that I put on a dashboard and in the layout template for my PMs, that shows them who completed a task on this porject.

It is a Note report.

The columns I use are Task Number, Task Name, Owner Name, and Entry Date.

The filter is...

auditText=Complete

auditText_Mod=cicontains

taskID_Mod=notblank

0694X00000C1gujQAB.pngHope that helps 🙂

Avatar

Level 4

Thanks, Anthony. I attempted this report but was not able to return accurate date when comparing the owner name to the task history for when a task was completed. I will keep this suggestion in mind though for other needs. 🙂

Avatar

Level 10

Interesting... I wonder what is causing the discrepancies. We've been using this report for about 5 years now and do our audits with it and haven't noticed any of the data been wrong.

Avatar

Level 9

Thanks @Anthony Imgrund‚

For sharing this filter code. I also used some of prompt to filter project owner and task status. I found after running the report that some of task appears more than one time. Is it any reason for that? Could you guide in this regard?

Mvh

Kundan.

Avatar

Level 10

Hi Kundan - My only thought is that maybe the task was completed and then reopened and then completed again. Are the date and time different between the two line items you see for the task?