I want to create a report that lists all Projects set to Project Status = Approved in the last month.  I am struggling to find a way to do this at the project level with the date limiter.  Any direction will be greatly appreciated.

 

The objective is to let people find newly approved projects so they can subscribe to them if they wish.

 

Terri

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by RandyRoberts

If you want want to see something based on when a field was changed, that woud be a Journal report.

2 replies

RandyRoberts
Community Advisor
RandyRobertsCommunity AdvisorAccepted solution
Community Advisor
February 14, 2023

If you want want to see something based on when a field was changed, that woud be a Journal report.

July 18, 2024

This sounds like something I've been requesting for some time now. Were you ever successful at building this report? We have 4 project coordinators who schedule projects. My goal is to be able to report on something like = how many projects did Jane schedule last month, last quarter, YTD or a specific time frame (when they change the project status from IN PLANNING to CURRENT)

RandyRoberts
Community Advisor
Community Advisor
July 18, 2024

This is a much easier report to build. In a project report you could create prompts for Entered By (User) and Actual Start Date, or something along those lines.