Report on user's OOO?

  • November 17, 2022
  • 2 replies
  • 1256 views

Is it possible to report on OOO logged in Workfront so that project managers be alerted scheduling impact across all projects?  We're looking for a solution so PMs don't have to go into each project to find this info.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

_Manish_Singh
Level 9
November 18, 2022

Creating a 'Time Off' report may help you:

Level 6
November 18, 2022

Thanks so much @_manish_singh !

Rafal_Bainie
Community Advisor
Community Advisor
November 18, 2022

Another way to do it, aside from already suggested Time Off report, is Calendar that would pull in all Time Off info

Level 6
November 18, 2022

Thank you @rafal_bainie 

_Manish_Singh
Level 9
November 19, 2022

Adding to the above, 'Calendar + Workload Balancer' would be a good combination to know scheduling impact.