Is it possible to report on OOO logged in Workfront so that project managers be alerted scheduling impact across all projects? We're looking for a solution so PMs don't have to go into each project to find this info.
Views
Replies
Total Likes
Creating a 'Time Off' report may help you:
Thanks so much @_Manish_Singh !
Views
Replies
Total Likes
Another way to do it, aside from already suggested Time Off report, is Calendar that would pull in all Time Off info
Agree, Calendar is a better option
Thank you @Rafal_Bainie
Views
Replies
Total Likes
Adding to the above, 'Calendar + Workload Balancer' would be a good combination to know scheduling impact.
Views
Replies
Total Likes