Project Templates Start and Completion Days
Hi guys, fairly new to Workfront (< 6 months) so apologies if this is a question that has been asked before A PM within the team wants to create a new project template but is struggling to make it work with regards to tasks starting and completing on set days. For example, Task 11 - Styling session - has 5 planned hours and needs to start and complete on the same day (day 24) but WF wants it to complete on day 25, using the Must Start On Task Constraint or a day earlier using the Must Finish on Task Constraint. The only way to get the start and completion days required is to reduce the Planned hours. The schedule assigned to the project is our default on which is set to 7.3 hours per day. If I set to a Fixed Date Constraint, it then zeros the duration. Thanks in advance.

