Project Templates Start and Completion Days | Community
Skip to main content
Level 2
December 19, 2022
Solved

Project Templates Start and Completion Days

  • December 19, 2022
  • 3 replies
  • 1215 views

Hi guys, fairly new to Workfront (< 6 months) so apologies if this is a question that has been asked before A PM within the team wants to create a new project template but is struggling to make it work with regards to tasks starting and completing on set days. For example, Task 11 - Styling session - has 5 planned hours and needs to start and complete on the same day (day 24) but WF wants it to complete on day 25, using the Must Start On Task Constraint or a day earlier using the Must Finish on Task Constraint. The only way to get the start and completion days required is to reduce the Planned hours. The schedule assigned to the project is our default on which is set to 7.3 hours per day. If I set to a Fixed Date Constraint, it then zeros the duration. Thanks in advance. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

Is it possible to switch the planned start and completion dates over to a format that additionally shows start and end times to see what's going on? 

3 replies

ChloeWY
Level 6
December 19, 2022

Hi @marktwo ,

I believe this will work if you use the As Soon As Possible constraint.  If there's a way you can use predecessors to build your timeline, you may want to consider this.  

markTwoAuthor
Level 2
December 19, 2022

Hi @chloewy Thanks for your answer, I can't seem to set a start and completion and have the constraint of As Soon As Possible. I'll take a look at using predecessors in order to control the timeline. Thanks again

skyehansen
Community Advisor
skyehansenCommunity AdvisorAccepted solution
Community Advisor
December 19, 2022

Is it possible to switch the planned start and completion dates over to a format that additionally shows start and end times to see what's going on? 

markTwoAuthor
Level 2
December 20, 2022

Hi @skyehansen I have been thinking about the issue a lot and if times as well as dates hold the key to it so thank you for mentioning it, I'll take a look and show times also. 

Level 3
December 26, 2022

Two suggestions:

1.  Check the starting time of the project and make sure it starts at the beginning of your work day.  That can sometimes throw off your days.  (I wish this was a project setting, to allow the user to set a default starting time when a project is created.)  

2.  Playing with different types of predecessors dependencies types might be helpful as well.  The system defaults to Finish to Start but one of the others may be more appropriate.  Check out this article:   https://experienceleague.adobe.com/docs/workfront/using/manage-work/tasks/use-task-predecessors/task-dependency-types.html?lang=en