Hi Workfront Community,

I'm looking for a solution that might be a little bit complex but your suggestions to achieve this are welcome. To be honest we are struggling to get something which looks very simple.

So.. we want to track projects that do NOT have a milestone linked on any of its tasks list. Example: Let's say we have Initiation, Design, Delivery and Go-Live milestones on a milestone path. I'm trying to identify projects that do not have "Go-Live" linked on its tasks. We want to make adding "Go-Live" as a mandate for our PMs to produce KPIs.

I believe we'll have to use 'collections' here because referencing does not work down the object hierarchy.

Thanks!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by imgrund

Hi - once you get the Milestone ID for Go-Live, you can use the below. Make sure you do all the regular project filters you want first. Then you switch to text mode and paste this underneath everything.

EXISTS:1:$$EXISTSMOD=NOTEXISTS

EXISTS:1:$$OBJCODE=TASK

EXISTS:1:milestoneID=c018bbf4237645cae053a7656a0a9384

EXISTS:1:projectID=FIELD:ID

*NOTE: Change the bold ID for your milestone ID

2 replies

imgrund
Adobe Employee
imgrundAdobe EmployeeAccepted solution
Adobe Employee
May 19, 2022

Hi - once you get the Milestone ID for Go-Live, you can use the below. Make sure you do all the regular project filters you want first. Then you switch to text mode and paste this underneath everything.

EXISTS:1:$$EXISTSMOD=NOTEXISTS

EXISTS:1:$$OBJCODE=TASK

EXISTS:1:milestoneID=c018bbf4237645cae053a7656a0a9384

EXISTS:1:projectID=FIELD:ID

*NOTE: Change the bold ID for your milestone ID

RandyRoberts
Community Advisor
Community Advisor
May 19, 2022

So, the project would have a milestone path but no tasks would be marked with the "Go-Live" milestone?

imgrund
Adobe Employee
Adobe Employee
May 19, 2022

Sorry Randy!! I just realized you weren't the original poster. HAHAHA! Friday Brain is starting a little early this week.

RandyRoberts
Community Advisor
Community Advisor
May 19, 2022

I saw this in one of your older posts and made a PDF to reference. Excellent info!