Question
Project Condition 'At Risk' when tasks are 'On Track'
Hi all, We have just launched Workfront and so far so good! Now that our executives are viewing reports, there is concern that 'the optics' of so many projects showing At Risk is not good. Upon further investigation, it seems that even if all remaining tasks are On Track, if there has been one task Completed Late, it will trigger that At Risk project condition, and the project cannot recover. Is that your experience? Any tricks or tips to have the project condition reflect that of say, the first task that all future tasks roll up under? I prefer to not use the Manual Condition as I want the system to tell us what is really happening, but people will lose faith in the system if all projects that had a Late Task show 'At Risk'... Any suggestions appreciated!
Amber Nyssen Tillamook County Creamery Association