In Workfront, Project Status is different from Project Condition. Project Status equates with if a Project is in Planning, Current, Complete, etc., and Project Condition equates to if the Project is On Time, At Risk or In Trouble. There are a lot of factors that go into how Workfront determines the 'condition' of a Project. You may find this Workfront Support article helpful in understanding why your Project may be At Risk: Understanding Project Condition , specifically How Progress Status of Tasks Determines the Condition of the Project. Is the last task on the Critical Path On Time as well? Workfront will denote At Risk for a Project, "when the Progress Status of the last task on the Critical Path is Behind or At Risk , then the Condition of the project is At Risk." Terry Hynd EBSCO Information Services