Question
Progress Status is "At Risk". Project Status is "Current"???
Hello all - ***EDITED QUESTION*** I'm hoping someone can shed some light on my problem - I got a notification on my project stating that the Progress Status of my project was At Risk. However, my Project Condition is On Target. I can't figure out why I'd be At Risk. All tasks in my critical path, including the last one, are On Time. Why wouldn't my Condition show At Risk on the project? James Foley, Senior Project Manager Western Alliance Bancorporation