Question
predecessor/constraint best practices when scheduling from completion
I need to set a up template that schedules from completion. Work needs to complete 12 weeks prior to the final step on this template. I've looked over the article at https://experience.workfront.com/s/article/Working-with-Templates-Scheduled-from-Completion-1245304368 but it doesn't get me the results I need. If I use Must Start On for the final steps constraint and As Late as Possible on all other steps, the dates calculate properly to show the latest each step can begin in order for all work to complete the day before the final step. I'm bumping into a way trying to leverage predecessors on that final step to build in a 12 week buffer between work completion and the final step. What am I missing? Catherine Hayes Manager, Business Analytics and Program Operations The Channel Company Westborough MA