Planner Report: actual hours are different from hours report | Community
Skip to main content
August 5, 2024
Question

Planner Report: actual hours are different from hours report

  • August 5, 2024
  • 2 replies
  • 1316 views

Hi, I pull the planner report for specific teams to show planned vs actuals. I noticed that the actuals in the planner report are not equaling the actuals in our hours reports (hours reports that are being pulled from timesheets). This is specific to certain tasks on a project or full projects. Is there a setting that could be prohibiting the planner report from pulling the actuals data in correctly?

 

In the attached instance, it's a task within a project that's not showing (2 hours off) but in some instances we have 20+ hours missing on either a full project or task within a project. 

 

Anyone have any thoughts??

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

skyehansen
Community Advisor and Adobe Champion
August 5, 2024

Your screenshots are trimmed too closely, and I'm not sure there's enough information here. Can you include the filters for your two reports?

LauraCa7Author
August 5, 2024

Hi - I just updated screenshots so you can see the job numbers. Both reports are filtered by portfolio (Portfolio contains "client name"). Thanks for the quick response!

skyehansen
Community Advisor and Adobe Champion
August 5, 2024

I still can't see very much. You're best off submitting a  case to the Support team, if your company policies are preventing you from sharing more information than this. The only thing I can mention at this point is that a number of things may prevent something from showing up in the resource management area. I know one of them is zero duration (so for example, if you have a task with no duration set, then this wouldn't show up in workload balancer), but you can look up all of them here:

https://experienceleague.adobe.com/en/docs/workfront/using/manage-resources/the-workload-balancer/overview-workload-balancer

Madalyn_Destafney
Community Advisor
Community Advisor
August 5, 2024

Are you sure you're pulling the 2 reports in an apples:apples way? Same timeframe, projects, teams, etc.?

If this helped you, please mark correct to help others : )
LauraCa7Author
August 5, 2024

Hi - thanks for responding! Yes, the hours report is pulled based on last months hours, by portfolio (portfolio contains <client name>). Resource Manager>Planner report is also looking at July hours, filtered by portfolio name ((portfolio contains <client name>). I suspect there's something in the project or task that's preventing hours to show in the resource management actuals view but I'm stumped on what it could be...

Madalyn_Destafney
Community Advisor
Community Advisor
August 5, 2024

And you're certain the planner report isn't showing Planned hours, just Actuals...

The hours report may also be pulling project and issue time and planner report showing only actuals on tasks or projects?

If this helped you, please mark correct to help others : )