Planned vs actual hours on a project

  • October 31, 2023
  • 1 reply
  • 914 views

Hello Workfront community,

 

Does anyone have text mode for the variance between planned and actual hours on a project please?

 

thanks

Jennifer

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by KellieGardner

I use this for the variance in actual vs planned. 

 

displayname=Hours Variance
textmode=true
valueexpression=SUB({workRequired},{actualWorkRequired})/60
valueformat=HTML

 

 

1 reply

JenlynMik
JenlynMikAuthor
Level 2
October 31, 2023

I think I have that now, but the count for the planned and actual hours on my chart is displaying the same count for each, but the details page shows the difference. Any suggestions?

 

KellieGardner
Community Advisor
KellieGardnerCommunity AdvisorAccepted solution
Community Advisor
October 31, 2023

I use this for the variance in actual vs planned. 

 

displayname=Hours Variance
textmode=true
valueexpression=SUB({workRequired},{actualWorkRequired})/60
valueformat=HTML

 

 

JenlynMik
JenlynMikAuthor
Level 2
November 8, 2023

Thank you Kellie!