Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!
SOLVED

Planned hours for tasks with multiple assignees

Avatar

Level 3

Our team is trying to encourage better collaboration amongst copywriters/designers and would like to start having 1 task that is assigned to the both of them so they can easily see who they are working with rather than 2 separate tasks for Copy & Design. 

 

Doing this seems to be throwing off our Planned Hours reporting for each user. Is there a way to allocate Planned Hours on 1 task that is assigned to multiple users? For example: a task that has 8 hours assigned to it; we want 3 of those hours for the Copywriter & 5 of those hours for the designer. Or is the only option to keep these as separate tasks?

 

Also open to other suggestions for anyone that may have a similar process

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

You have to do a few extra steps. Easiest way I've found is to click on the people icon on the assignments box from the project interface.

KellieGardner_0-1730320469342.png

 

Then it will give you a pop up where you can allocate the hours by user. (note: your duration type should be simple if you want to allocate hours vs percentages of work)

 

KellieGardner_1-1730320512773.png

 

 




View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

You have to do a few extra steps. Easiest way I've found is to click on the people icon on the assignments box from the project interface.

KellieGardner_0-1730320469342.png

 

Then it will give you a pop up where you can allocate the hours by user. (note: your duration type should be simple if you want to allocate hours vs percentages of work)

 

KellieGardner_1-1730320512773.png

 

 




Avatar

Level 3

AH I knew there had to be a way!!! Thank you so much, this is perfect. 

 

Is there anyway to have the Duration Type default to Simple?