Planned Dates Don't Calculate
Every now and then, for reasons that are unclear, my dates don't calculate. In this case it skips Thursday. If I make the In Market Date Feb 6, the Mail Date switches to Friday Jan 24. The rest of the plan is on schedule and working perfectly right up until the second to last task. There is nothing marked done, it doesn't start until next week, all constraints are ASAP. I am going out of my mind. Not sure if the screenshot will come through of the problem rows. Any magic wands?
Jill Ackerman