Parent tasks not automatically updating when two statuses equate as "New"
Not sure if this is expected behaviour or not, but looking for suggestions -
I have two task statuses that equate to "New", they are 'Not Ready' and 'New'.
I have set 'Not Ready' to be the default task status for new tasks on my projects, and project settings to 'Automatically update' for the parent tasks, however when I change child tasks to 'New' it doesn't automatically update the Parent task to show New.
I'm assuming this is because both statuses equate to New, so the system doesn't recognise a change of status?
I'm using the two statuses to differentiate between tasks ready for my resourcing team to schedule, vs those that are not ready to be assigned to a specific team member yet, and can't have this action at a project level as our business can't schedule too far in advance for complex projects.
Does anyone have any alternative suggestions that would work? It's not a huge issue with the Parent Tasks staying as 'Not Ready', but isn't a true reflection of status, if all the tasks underneath are new and scheduled with staff.
I can't swap the status update to be manual as I need it to calculate up "percentage complete" automatically everywhere else.