Parent tasks % complete not updating to specific percentages
Hi WF Community,
Does anyone know if there's a project setting that will allow for parent tasks to update to specific percent complete values (e.g. 56%) based on the percent complete values of its sub-tasks?
For example:
- Parent Task A has 2 sub-tasks
- Sub-Task 1 has a % complete of 50%
- Sub-Task 2 has a % complete of 10%
- Result: Parent Task A should have a percent complete value of 30%
Right now, the only time a parent task's percent complete value updates is when it's sub-tasks are fully complete (100%), and thus, the parent tasks updates from 0% to 100% (but nothing in between).
Thanks.
Nick