Hi All, I'm doing a test to see how we can use Milestones on our projects, and had a question on how the system "orders" these milestones in a project view. As you can see, the dates are not organized from left to right, I can't figure out how the system is "ordering" the milestones. Milestones at the end of the project are appearing first, and milestones at the beginning of the project are appearing in the middle. Andrew Daniels Gartner, Inc.
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Christina_Jarosz
Level 9
February 14, 2020
Hey Andrew, These are setup in the order of your milestone path. In your milestone path, internal review is likely first. The dates coincide with your milestone tasks in your project schedule.
Level 2
February 14, 2020
That's so strange! I set them up in the proper order, but after saving and reopening, the order had changed. I figured it wasn't important. I just went through and reordered them, which worked like a charm. Thanks for the help! Andrew Daniels Gartner, Inc.