Hi everyone!
I hope you are doing well today. We are wanting to track project completion and also user usage within Workfront. I am wanting to build two reports-- one that shows the number of times the planned completion date has been changed on a project, perhaps sorted by the projects with the greatest number of date changes to the least. The second report would be a task report that shows which tasks have had their due dates changed the most, grouped by user. We're wanting to determine if our users are just pushing the due dates out on tasks.
Do you have any suggestions of how to go about this? Ideally I would like a column within the report that shows the number of times the date was changed, either that or the number of changes listed within the grouping header.
Thank you for your help! This community is great!
Leah
Topics help categorize Community content and increase your ability to discover relevant content.
Hi Leah,
I can offer a few options:
Regards,
Doug
Views
Replies
Total Likes
Hey @Doug_Den_Hoed__AtAppStore
This is some great information, I am trying to execute your idea number two. I'm just a bit confused, I'm wanting to filter on Projects that have a " {user} has changed the due date" but I can't see which field this would be in the notes report. This is a system-tracked update. I am so close just can't get this last step! Any help would be appreciated.
Views
Replies
Total Likes
Hi @AnthonyCAANZ,
When creating such a Notes report, I suggest you search either the "Notes Text" column (for user entered information), and/or the "Audit Text" column (for system generated information). In the case of my idea number two, the latter would apply. Good luck!
Regards,
Doug
Views
Replies
Total Likes
Thanks Doug for the quick response, Still can't get it right but I'll keep trying!