Has anyone created a column to show the remaining planned labor costs for a project using statuses? I want to see what the planned labor cost is for the whole project regardless of the task status in one column and in another column see the remaining planned labor costs of non completed tasks. Not using actual hours vs remaining planned. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Doug_Den_Hoed_AtAppStore


Hi @brittb,

 

I invite you to review our AFA Burn Report solution video and if it seems like a potential fit would be happy to chat further via doug.denhoed@atappstore.com.

 

Regards,

Doug

1 reply

Doug_Den_Hoed_AtAppStore
Community Advisor
Doug_Den_Hoed_AtAppStoreCommunity AdvisorAccepted solution
Community Advisor
May 4, 2024


Hi @brittb,

 

I invite you to review our AFA Burn Report solution video and if it seems like a potential fit would be happy to chat further via doug.denhoed@atappstore.com.

 