Negative "sf" predecessor for "schedule meeting"-style task | Community
Skip to main content
Level 5
May 29, 2025
Solved

Negative "sf" predecessor for "schedule meeting"-style task

  • May 29, 2025
  • 1 reply
  • 473 views

I'm looking to setup two tasks -- one for "Meeting" and another for "Schedule Meeting".  I'd like the "Schedule Meeting" one to dynamically start 2 weeks prior to the "Meeting" task, which has other dependencies on the rest of the project.

I've tried a number of different options related to both predecessors and constraints.  Anyone have any thoughts on how to do it?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

what initially occurs to me is that workfront doesn't have a listing for "w" to mean "week" in the lag types overview:

https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/tasks/use-task-predecessors/lag-types

 

If I wanted to do 2 weeks, I'd indicate it using "10d" and start experimenting from there. 

1 reply

skyehansen
Community Advisor
skyehansenCommunity AdvisorAccepted solution
May 29, 2025

what initially occurs to me is that workfront doesn't have a listing for "w" to mean "week" in the lag types overview:

https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/tasks/use-task-predecessors/lag-types

 

If I wanted to do 2 weeks, I'd indicate it using "10d" and start experimenting from there. 

cvergesAuthor
Level 5
May 29, 2025

OMG that totally worked!  It's nuts, the UI accepts "2w" but to your point, it only does the calculation properly with "10d".  It looks from that link like the "w" means "day of week", which is bonkers.

skyehansen
Community Advisor
May 29, 2025

haha I'm sure someone wants something to start based on what day of the week it is. Luckily my users have never gotten that deep into predecessors.