Need help with Sub formula in Project Level Report
Hi Friends!
In a project level report, we are trying to create a custom column that portrays the difference between 2 custom fields. The below are the custom fields (their names in bold, sentence below is how the custom fields are calculated):
PIM | Task Cycle Time to In Market Date - Work Min Diff
ROUND(WORKMINUTESDIFF({project}.{program}.{DE:PIM | Program In Market Date},{handoffDate})/480)
PIM | Program SLA Sum
SUM({DE:RED | T-Shirt SLA},{DE:PIM | T-Shirt Deployment},{DE:PIM | Engagement SLA},{DE:PIM | Creative Brief SLA},{DE:PIM | Strategy SLA})
Below was our proposed difference column between these two fields:
displayname=Cycle Time Variance from SLA
valueexpression=SUB({DE:project:program:PIM | Program SLA Sum},{DE:PIM | Task Cycle Time to In Market Date - Work Min Diff})
valueformat=HTML
When this runs, it only recognizes the value that is in the "DE:PIM | Task Cycle Time to In Market Date - Work Min Diff" field. So it feels like something is off with the "DE:project:program:PIM" portion.
Please let me know your thoughts!