Need help with report filters

Avatar

Level 1

Hi all,

 

What is the expression to be used in filters to fetch projects that are overdue past 30days from planned completion date.

 

Thanks in advance

1 Accepted Solution

Avatar

Correct answer by
Community Advisor
1 Reply

Avatar

Correct answer by
Community Advisor

KellieGardner_2-1750090070076.png