Hi,
My projects have tasks with multiple people assigned to them. Yet workfront only allows for a primary task owner. The report I view only shows the status based on the primary task owner. When I view reports for the secondary task owners the task doesn't show up on their list, because it's on the primary's list. How can I change that? Is there a way to adjust the reporting so the task shows up on the secondary task owners report as well? Thanks.
Solved! Go to Solution.
Views
Replies
Total Likes
You can use the filter of 'assignment users name' in a task report - that will show all assignees, not just primary!
Hi Linda,
What type of report are you using?
I would recommend using an assignment report as this will show tasks (or issues) based on who is assigned, regardless of whether or not they are a primary or secondary assignee. Using this type of report, you will get a line item for every assignee (as opposed to a line item for every task if you were used a task report)
Best Regards
Rich
Views
Replies
Total Likes
Hi Rich! Thank you so much for your quick response, I'll look into it and let you know if I have more questions.
Views
Replies
Total Likes
You can use the filter of 'assignment users name' in a task report - that will show all assignees, not just primary!
Thank you so much for the tip!
No problem! Please mark the answer correct if that helped you out to help others : )