link between tasks frm the project pullng into the workload balancer? | Community
Skip to main content
Level 4
July 19, 2023
Solved

link between tasks frm the project pullng into the workload balancer?

  • July 19, 2023
  • 1 reply
  • 721 views

I'm sure this is basic but what am I missing - what is the link between tasks from the project pulling into the workload balancer?

 

I have 4 tasks assigned to a worker but only 3 of the tasks show up in the workload balancer. What is the link that creates or causes this? Screenshts attached

Thank you!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Richard_Le_

Hi,

 

Your final sign off task does not have a duration. This is likely why it's not appearing.

 

If you set the duration to something greater than 0, it should appear in the balancer.

 

Best Regards,

Rich. 

 

 

1 reply

Richard_Le_Community AdvisorAccepted solution
Community Advisor
July 19, 2023

Hi,

 

Your final sign off task does not have a duration. This is likely why it's not appearing.

 

If you set the duration to something greater than 0, it should appear in the balancer.

 

Best Regards,

Rich. 

 

 

JaxelleAuthor
Level 4
July 19, 2023

Woops - thanks Rich! I thought it could be pulled from the plan hours, so the root is from the duration?

Community Advisor
July 19, 2023

No problem, glad I could help!

 

There's many reasons why a task or issue might not appear. Dates, assignments, hours and duration can all have an impact on what is displayed. You can read more on the Workload balancer here

 

Best Regards,

Rich.