Hi, I think your best workaround for this is to dynamically intake items to your board based on the assignees, tasks, issues or projects you're looking for, then you move the cards to the appropriate column, like an Events column. The column itself doesn't have to be set up to bring in something automatically, it can be anything but you just may have to take time moving cards under it. In the top right of your Board, select Configure > Dynamically intake checkbox:

Then you can set a filter to hone your results of what is brought in as cards dynamically as needed on the left side of the Board:

Click any card's 3 dots to move it to a column:

More on this here: https://experienceleague.adobe.com/docs/workfront/using/agile/agile-planning-boards/add-intake-colum...
If this helped you, please mark correct to help others : )