Kanban Board - "Complete" items drop off

Avatar

Level 2

When do items in the "Complete" column on the Kanban board drop off? If they never drop off, it will become an ever-increasing list. If it is based on project status, which status triggers it to drop off?

2 返信

Avatar

Level 8

I had asked Support this question last year, and they had indicated that items will remain in the Completed column on the Kanban board for 2 weeks.

Avatar

Level 2

You can specify how long you want them to remain on the board. See the last item on this page.