We created several custom tasks views. We are unsure why in these views certain task names show italicized. See attachment.
In the predefined views from Workfront we don't see this behavior.
Appreciate any insight.
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
I think we solved our question. It appears italic tasks are the ones on the critical path. When we use the built-in task view of Status all italic tasks show the critical flag active.
Views
Replies
Total Likes
I think we solved our question. It appears italic tasks are the ones on the critical path. When we use the built-in task view of Status all italic tasks show the critical flag active.
Views
Replies
Total Likes
Thank you for sharing your insight! Now we know what to look for in the future.