It appears that tasks can be started and completed without completing the applicable task's predecessor.

 

How can I configure Workfront to prevent this type of behavior and enforce a user to first complete the Task's predecessor?

 

Or, is this a bug?

Best answer by Richard_Le_

HI,

 

You are able to enforce the predecessor relationship, which will prevent the successor task from being started (i.e., status being changed to "In Progress") until the predecessing task is complete. You can read more on this functionality here.

 

When entering your predecessor task number, simply put "e" after it. i.e., If task 2 was dependant on task 1, I would type "1e" in the predecessor column.

 

Best Regards,

Rich. 

1 reply

Richard_Le_Community AdvisorAccepted solution
Community Advisor
March 23, 2023

HI,

 

You are able to enforce the predecessor relationship, which will prevent the successor task from being started (i.e., status being changed to "In Progress") until the predecessing task is complete. You can read more on this functionality here.

 

When entering your predecessor task number, simply put "e" after it. i.e., If task 2 was dependant on task 1, I would type "1e" in the predecessor column.

 

Best Regards,

Rich. 