It appears that tasks can be started and completed without completing the applicable task's predecessor.
How can I configure Workfront to prevent this type of behavior and enforce a user to first complete the Task's predecessor?
Or, is this a bug?
Solved! Go to Solution.
Views
Replies
Total Likes
HI,
You are able to enforce the predecessor relationship, which will prevent the successor task from being started (i.e., status being changed to "In Progress") until the predecessing task is complete. You can read more on this functionality here.
When entering your predecessor task number, simply put "e" after it. i.e., If task 2 was dependant on task 1, I would type "1e" in the predecessor column.
Best Regards,
Rich.
HI,
You are able to enforce the predecessor relationship, which will prevent the successor task from being started (i.e., status being changed to "In Progress") until the predecessing task is complete. You can read more on this functionality here.
When entering your predecessor task number, simply put "e" after it. i.e., If task 2 was dependant on task 1, I would type "1e" in the predecessor column.
Best Regards,
Rich.
Thank you so much!
Views
Replies
Total Likes
Views
Likes
Replies
Views
Likes
Replies