Issues with Due Dates

  • August 14, 2023
  • 1 reply
  • 531 views

Hi Folks, 

 

Is anyone else experiencing challenges with project due dates? Several members of my team is reporting that when they set due dates for new tasks within a project, the system changes the due date to a date in 2024. I'm also seeing the same issue when I try to assign due dates. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Heather_Kulbacki

@louisamf a few things to look at:

Schedule Mode on the project

Task constraint

Task duration

Task predecessors

 

e.g. if the Schedule Mode is "Start Date" and the project's planned start date is sometime in 2024, with a constraint of as soon as possible, a duration of 2, and no predecessors, your task due date would be 2 days after the planned start date of the project.

or if the Schedule Mode is set to "Completion Date" all tasks will default to on or before the planned completion date of the project, unless that date is adjusted in the Edit area of the project.

1 reply

Heather_Kulbacki
Community Advisor
Heather_KulbackiCommunity AdvisorAccepted solution
Community Advisor
August 15, 2023

@louisamf a few things to look at:

Schedule Mode on the project

Task constraint

Task duration

Task predecessors

 

e.g. if the Schedule Mode is "Start Date" and the project's planned start date is sometime in 2024, with a constraint of as soon as possible, a duration of 2, and no predecessors, your task due date would be 2 days after the planned start date of the project.

or if the Schedule Mode is set to "Completion Date" all tasks will default to on or before the planned completion date of the project, unless that date is adjusted in the Edit area of the project.