Issue Replicating Project Templates in Production from the Sandbox Environment

  • May 9, 2024
  • 1 reply
  • 1088 views

I'm attempting to rebuild templates that I created within my sandbox environment but when I build them in prod the total project duration is completely off. I've included a screenshot below of the template I'm trying to recreate

 

As you can see the development & review summary task says the steps will take 60 days in the sandbox but the same template with all the same tasks, durations, task constraints, and predecessors is saying it will take 112 days in production

 

Would love to know if anyone has seen issues like this before! I've submitted a support ticket but they haven't responded to any of my emails : P. I'll close this question and include the solution if support is able to figure out what is going on before we can!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by MatthewLi1

no worries and good luck with Support. The only other thing I can suggest would be to recalculate the template timeline if you haven't already done this.


Circling back to confirm that I did try recalculating the template timeline. I tried working with support and hopped on a call with them to help them troubleshoot but they don't know what's causing the issue after a month of troubleshooting so it appears this is a bug without any solution

1 reply

skyehansen
Community Advisor
May 9, 2024

Can you post a screenshot of a view that includes the task constraint, start day, and completion day as well, please.

MatthewLi1
Level 3
May 9, 2024

Hi @skyehansen, here's a screenshot with those columns! 

Looks like the issue may be with tasks 13 &14 as they are set to as late as possible but not connected by predecessors to the go live which needs to finish at a set time. Regardless though, I'm still confused by why the dates are so different for both.

skyehansen
Community Advisor
May 9, 2024

I have recreated the templates from scratch and gotten the timing closer to what I was expecting to see. I'm just still unsure of what is causing the project to complete in twice the time when I put the same template from our sandbox into prod. I would think the project would calculate back from the final task's due date which was my intention but it's adding 60 days to the project that I can't remove even when I edit the start and complete day columns. 

 

Either way, I'll try to work through this with support if they can find the time to respond to my emails. Thanks for your help here, was great to at least get some eyes on this so I know I wasn't missing something simple!


no worries and good luck with Support. The only other thing I can suggest would be to recalculate the template timeline if you haven't already done this.