[Issue list with column of corresponding Task Item]\n\nHi all, \nI would like to see in the issue item list, the corresponding task. Can anyone help me?\nThank you.\nBR,\nAnna-Katharina

Avatar

Level 2

To every task an issue (action) can be added. This can be easily done, and I do see all issues in my issue item list. However, I am missing a column, that shows me the corresponding task item.

I would like to see in my issue item list, a column which shows me the corresponding task item.

Can someone please help me, how do I do this. I do have admin rights.

Thank you.

Best regards,

Katharina

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 10

Hi Anna-Katharina,

By using the Issue > Source, you can retrieve the task the issue resides on.0690z000008aSndAAE.png

Thanks,

Narayan

Avatar

Level 2

‚Hi Narayan,

Thank you so much. I tried it just now - that's what I am looking for 🙂

Best wishes from Vienna,

Anna-Katharina