Ideally I'd like a task report that pulls in the planned hours and actuals hours for a specific role or user when there are multiple roles/users assigned to the same task.

I've tried an Assignments report - that gives me the planned hours for just a single assignee on the task when there are multiple assignees, but only gives me actual hours for the whole task.

I've tried an Hours report grouped by task - that gives me the actual hours for just the single assignee, but only gives me the planned hours for the whole task.

I'm guessing this is something I need to bring up next time I talk to the New Reporting team, but still hopeful that someone here has something we haven't thought of.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by TealeMcCleaf

Hi Heather,

Give this a try...

valueexpression=IF(ISBLANK({assignedToID}),CONCAT({role}.{name}," - ",{actualWorkCompleted}/60,' / ',{workRequired}/60," Hours"),CONCAT({assignedTo}.{name}," - ",{actualWorkCompleted}/60,' / ',{workRequired}/60," Hours"))

listdelimiter=<br>

listmethod=nested(assignments).lists

valueformat=HTML

displayname=Assignment Breakdown

textmode=true

type=iterate

I have this in a column on a Task report and it pulls the User and Job Role assigned, their individual allocation of time on the task and the actual / planned hours.

Hope this helps,

Teale

1 reply

TealeMcCleafAccepted solution
Level 6
March 13, 2021

Hi Heather,

Give this a try...

valueexpression=IF(ISBLANK({assignedToID}),CONCAT({role}.{name}," - ",{actualWorkCompleted}/60,' / ',{workRequired}/60," Hours"),CONCAT({assignedTo}.{name}," - ",{actualWorkCompleted}/60,' / ',{workRequired}/60," Hours"))

listdelimiter=<br>

listmethod=nested(assignments).lists

valueformat=HTML

displayname=Assignment Breakdown

textmode=true

type=iterate

I have this in a column on a Task report and it pulls the User and Job Role assigned, their individual allocation of time on the task and the actual / planned hours.

Hope this helps,

Teale

Heather_Kulbacki
Community Advisor
Community Advisor
March 15, 2021

Thank you! This was helpful.

Once I added this column into a task report, I was asked if we could get the planned/actuals for a particular user instead of all users on the task. But with this as the base, a little tweaking got us exactly what we needed.

Level 4
January 18, 2022

Hi @Heather Kulbacki‚ ,

I'm trying to make this work in a calculated column to show the assignment planned hours for the particular user, filtered with the $$USER.ID wildcard.

Could you specify what little tweaking you did to make this info user-specific instead of all users on the task?

Hopefully, that will help me finalize my calculation.

But maybe it's not even possible what I want 😏 .

Kind regards,

Femke