Is there a date field that shows when a task becomes active? | Community
Skip to main content
Level 4
March 16, 2023
Solved

Is there a date field that shows when a task becomes active?

  • March 16, 2023
  • 2 replies
  • 1297 views

Hi All,

I'm trying to see if there is a native field that displays the date a task becomes active?  Actual, and projected date fields aren't giving me that date.  Any suggestions would be appreciated.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by KellieGardner

If you are looking to see when a task became ready to work on based on predecessors you could use Hand Off Date.

 

The Handoff Date is the date that a task becomes available for work. This typically means that its predecessors have resolved and the assignee of the task can start working on it.

2 replies

Madalyn_Destafney
Community Advisor
Community Advisor
March 16, 2023

Hi, help me clarify what exactly you're looking for:
- Are you looking to see the date the assignee commits to the task/hits work on it and therefore changing the progress to In Progress? If so, that is something you can include in your updates feed on a task...If you're looking for a detailed report on task status changes like this, I recommend a journal entry report.

- Are you looking to see the entry/creation date of the task, if so, that is the 'task entry' date in task report.

If this helped you, please mark correct to help others : )
Level 4
March 16, 2023

Hi Madalyn, I've created a custom report that tracks dates (actual start - projected/actual completion) of tasks within a project horizontally.  It works really well and updates the subsequent tasks in each column based on the change in dates of its predecessors, however when I've run test it doesn't capture the dead time (it doesn't show the date a task has become active, just when someone changes the status or adds time to it).  So say if a previous task is completed on 3/13 but the next task isn't touched by a team member until 3/16, there are three days unaccounted for in the report. It should say 3/13 - 3/17, not 3/16 - 3/17.

KellieGardner
Community Advisor
KellieGardnerCommunity AdvisorAccepted solution
Community Advisor
March 16, 2023

If you are looking to see when a task became ready to work on based on predecessors you could use Hand Off Date.

 

The Handoff Date is the date that a task becomes available for work. This typically means that its predecessors have resolved and the assignee of the task can start working on it.

Level 4
March 16, 2023

Is that an actual field in WF?  Never heard of it before.

 

Level 4
March 16, 2023

Yes, you should be able to access it in a view or a report. 


IT WORKED!!!