Is it possible to report out tasks sorted by each resource assigned to it? | Community
Skip to main content
Level 2
May 7, 2020
Question

Is it possible to report out tasks sorted by each resource assigned to it?

  • May 7, 2020
  • 2 replies
  • 638 views

I have a report that shows all in-progress tasks by resource for all projects. The issue is with tasks that have multiple resources assigned to them. The report only shows that task under one of the assigned resources. That task does not show under the other assigned resources. I want the task to show up under each resource's name. We want to use this report to drive a daily scrum for the team. I know the issue is that Assigned allows for multiple values. But, there has to be a way to have a report that shows which tasks each resource is working on. Does anyone have something like this? I tried to drive this from the Assigned table but it does not allow me access to the task table.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
May 8, 2020

Hi Chris,

Hmm. It sounds like you're on the right track by building an Assignment report, in which you could then (for example) group by User Name and show a column for the Task Name.

Regards,

Doug

Level 2
May 8, 2020

Chris,

I agree with Doug, special times call for special actions. Using a project, or projects, to track this information is probably going to be the easiest way to track it now, and to be able to report on it later if needed.

Regards,

Andy

Level 3
May 11, 2020

Are you or have you considered using an Agile Team and filtering in the Team view by user on the Kanban board?