In a task report > Groupings > Matrix Settings, for Task Estimate, how can we get the Matrix table value to show sum rather than count? | Community
Skip to main content
Level 2
August 13, 2020
Question

In a task report > Groupings > Matrix Settings, for Task Estimate, how can we get the Matrix table value to show sum rather than count?

  • August 13, 2020
  • 1 reply
  • 616 views

Hi everyone,

I'm trying to make an estimated hours matrix table per iteration for a client.

Unfortunately, the value is only counting the amount of tasks we have in the iterations rather than summing up the estimated hours, is there anyway to get around this? Ideally I just want it to be sum, rather than count? But the option is not showing for myself, is there anything I can input into text mode to allow this to occur?

I have checked the hours report, and doesn't have the options for team name, or iteration name, so it won't work on there.

Thanks!

Jez

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
August 13, 2020
Hi Jez, I suggest you add the Planned Hours column to the view of your report and (here’s the trick) choose to “sum” that column, then see if “sum” is then be available in addition to Record Count on the Matrix (as is the case for charts). Regards, Doug
JezAkAuthor
Level 2
August 13, 2020

Hi Doug,

Thanks, the sum is available. But unfortunately, then the planned hours then takes place of the estimated hours. Planned hours would work, but one iteration was on points, so it throws it off. I've opted to go for story points now.

Thanks!

Jez