I need additional calculation for "Current Task" report/view, or possibly a filter for it.
My takeaway from 2019 LEAP was the "Current Task" calculation view....problem I am having now is with a scrum team that uses more than one schedule.....thus returning more info than I'd want a customer to see....I JUST need the first task to show in column.
so given this provided calculation:
displayname=Current Task(s)
listdelimiter=­
listmethod=nested(tasks).lists
textmode=true
type=iterate
valueexpression=IF({numberOfChildren}>0,"",IF(ISBLANK({handoffDate}),"",IF(ISBLANK({actualCompletionDate}),CONCAT(" | ",{name}),"")))
valueformat=HTML
I get this - the first one in bold is accurate and I don't need anything that comes after
| Review p2 - make edits | Production task - Send P3 to customer | Production task - Make P2 changes - Complete Task in Sprint AND Production Template | Production task - Approve as FInal - Complete Task in Sprint AND Production Template | Post-Production task - Share Final PDF | Post-Production task - DSF # w/Customer | Production task - Make P3 changes - Complete Task in Sprint AND Production Template | Set Project Status to Complete
I have submitted a ticket but thought I'd double up in hope for quickest solve.....help and thank you