I have a question, because I know I am not crazy, when was the On Hold status updated to where it now removes tasks from the Work List?
I know last year I learned at LEAP 2019 that the On Hold would not remove a person's tasks from their Work List and learned that we should make a separate status, such as On Hold-Update My Work.
As we are now putting more projects on hold I did some testing and now the On Hold status removes the tasks from the Work List. Just curious as I recommended to our PM team to use the status I created of On Hold-Update My Work, even though it wouldn't remove the tasks that were already committed and put the project in a Planning Status, I thought that was the best COA.
Now I feel crazy and cannot find the enhancement or product release where the On Hold status was corrected to remove tasks from the Work List.