How to see the Burndown chart in Agile?

  • November 9, 2020
  • 2 답변들
  • 964 조회

Hi

How to see the Burndown chart in Agile?

Mvh

Kundan

이 주제는 답변이 닫혔습니다.
최고의 답변: Richard_Le_

Hi Kundan,

The burndown chart is visible in the teams area of Workfront when the team is set up as an Agile Scrum team and an iteration is in flight.

Burndown charts are designed to visually represent how your work is progressing through an iteration, it shows what work is left to do vs time left within current iteration (note that a burndown chart will not appear for kanban teams as iterations are not traditionally used kanban methodology). If you have teams who use scrum, you will need to set them up as a scrum team within workfront and once they have planned an iteration into the system and added their stories from the backlog, a burndown chart will appear for the current iteration.

Best Regards,

Rich.

2 답변

Community Advisor
November 9, 2020

Hi Kundan,

The burndown chart is visible in the teams area of Workfront when the team is set up as an Agile Scrum team and an iteration is in flight.

Burndown charts are designed to visually represent how your work is progressing through an iteration, it shows what work is left to do vs time left within current iteration (note that a burndown chart will not appear for kanban teams as iterations are not traditionally used kanban methodology). If you have teams who use scrum, you will need to set them up as a scrum team within workfront and once they have planned an iteration into the system and added their stories from the backlog, a burndown chart will appear for the current iteration.

Best Regards,

Rich.

Kundanism
Kundanism작성자
Level 10
November 23, 2020

Thanks a lot @Richard Leek‚

Great inputs for me. Have a great day ahead!

Mvh.

Kundan.

Level 2
November 10, 2020

Also worth mentioning Kundan that the burndown chart are useful if your team is committing to an amount of work in an iteration. If teams are adding workload throughout the iteration then the value of these charts demises.

If you have further Agile questions I am happy to assist.

Damian

Kundanism
Kundanism작성자
Level 10
November 23, 2020

Thank you @Damian Rushton‚

I really appreciate your help, and sure I will come back since have many questions for agile.

Do you have some ready to read and learn document / videos to get guidance in this regard?

Very interested to implement this in our organisation.

Have a nice day!

Mvh

Kundan.