Is there a way to distribute planned hours manually across the duration of a task? (from a request, not a project).

 

At the moment when a new request is being submitted and for example if I assign 3 workers to the request its showing up in the workload balancer as 2 each's for each worker when in reality this is not the correct hours.

 

Is there a way to do it manually / set different hours like you can do from tasks when converting a request into a project?

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Heather_Kulbacki

This article talks about assigning resources to tasks and issues Create Advanced Assignments

Item #7, the TIP listed there, the 2nd bullet states: "You cannot manually modify assignment allocations on issues"

 

1 reply

Heather_Kulbacki
Community Advisor
Heather_KulbackiCommunity AdvisorAccepted solution
Community Advisor
August 18, 2023

This article talks about assigning resources to tasks and issues Create Advanced Assignments

Item #7, the TIP listed there, the 2nd bullet states: "You cannot manually modify assignment allocations on issues"