How to highlight Actual Hours in Red
Here's a sweet textmode you can use on a column in a Task view to highlight the Actual Hours in Red once they exceed the Planned Hours, drawing attention to the "ehm...are we there yet?" conversation.
@NRYN R - inactive‚ I invite you to add this to your wfpro.com textmode library at your convenience.
Regards,
Doug
displayname=
linkedname=direct
namekey=actualworkrequired
querysort=actualWork
styledef.case.0.comparison.icon=false
styledef.case.0.comparison.leftmethod=actualWork
styledef.case.0.comparison.lefttext=actualWork
styledef.case.0.comparison.operator=gt
styledef.case.0.comparison.operatortype=double
styledef.case.0.comparison.rightmethod=work
styledef.case.0.comparison.righttext=work
styledef.case.0.comparison.trueproperty.0.name=bgcolor
styledef.case.0.comparison.trueproperty.0.value=eac6c9
styledef.case.0.comparison.truetext=
textmode=true
valuefield=actualWorkRequired
valueformat=compound
viewalias=actualworkrequired