How to create nested sub task in Workfront by using fusion? | Community
Skip to main content
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by lgaertner

Hi,

 

to create a child / subtask, you just need to add the field parentID to your Create Record module and map the id of the parent task to it.

 

Regards

Lars

1 reply

lgaertner
lgaertnerAccepted solution
March 21, 2025

Hi,

 

to create a child / subtask, you just need to add the field parentID to your Create Record module and map the id of the parent task to it.

 

Regards

Lars

March 21, 2025

If I want to create sub task under sub task, is it same way to map?

lgaertner
March 21, 2025

Correct, the "sub sub task" would get the sub tasks ID mapped to the parentID field.