Question

How does a project's condition is calculated

  • January 9, 2024
  • 1 reply
  • 730 views

Hi,

has anyone know how the project's condition is calculated?

I found an article discussing this here but still wondering if there is like a granular level calculation.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

KellieGardner
Community Advisor
Community Advisor
January 9, 2024

That's pretty much it.

 

Basically if you have tasks that are showing behind, at risk or late that results in the dates of your projected or estimated completion dates out, then the project will go into at risk, behind, or late condition.

January 10, 2024

Great. Appreciate it. 🙂