Hi TealeMc4,
Thank for the reply.
I am sure this is because I misinterpreted your answer, but I am not getting the expected result.
Below is a screenshot of what I think you suggested, but it shows Task B finishing before Task A.
I want Task B to be able to finish no later than 2 days after Task A finishes. So, in my example, Task A starts on Monday, 11 November, and can finish on Friday, 15th. Task B can start on Tuesday 12th November and finish no later than 2 days after Task A finishes. This puts Task B's finish date as Wednesday, 20th November (assuming Weekends are non-working days).
I thought the answer might be to set the duration of Task B to be 6 days and not 1? But the issue is if Task A finishes early, then Task B should also finish early, but if I set the duration of Task B to be 6 days, then it will not finish early based on Task A being completed before the planned completion date.