How do I set up Task B that can start when Task A starts and can finish up to two days after Task A is finished
New to Workfront but doing ok on working most things out.
However, hoping someone can help with this one.
I have Task A that has a duration of 4 days.
I then have task B that has a duration of 1 day.
Task B can start one day after Task A starts and can finish up to two days after task A is done.
How do I set up task B to reflect this as it is like Task be has two predecessors, both being Task A.
One would be SS+1d
One would be FF+2d
But you cannot have a Task with two predecessors from the same Task. Well, not that I have found.
Thanks for any help with this one.