I am currently making a report, which will display the the tasks which is been completed, within the last 7 days, and also display the last comment for each of the task, any idea how to do the same.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by KellieGardner

You are trying to add a column that displays the last update made on the task? 

 

You should be able to use Last Note Note Text

 

 

1 reply

KellieGardner
Community Advisor
KellieGardnerCommunity AdvisorAccepted solution
Community Advisor
February 6, 2024

You are trying to add a column that displays the last update made on the task? 

 

You should be able to use Last Note Note Text

 

 

VanishVeAuthor
February 6, 2024

Thanks for the answer this really help a lot.