Gantt Chart View - Month names missing | Community
Skip to main content
Level 2
October 14, 2024
Question

Gantt Chart View - Month names missing

  • October 14, 2024
  • 3 replies
  • 856 views

Good morning all,

Myself and my colleagues have recently noticed that the months are not displaying on the Gantt chart view of any project we work on. As it has affected several of us, i assume this isn't a user error, but potentially a system change that has caused this.

Does anyone know how to display the months again in the Gantt Chart view? Please see attached a screenshot to see the current view (months should be displaying under 'Quarter').

Thanks in advance

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

3 replies

Sven-atClient
Level 3
October 14, 2024

@jameswi7 

 

that's a bug - day names are missing as well. Have you filed a ticket? 

Sven-atClient
Level 3
October 14, 2024

@jameswi7 
Adobe seems aware - i see the same issue. 

Thank you for contacting Adobe Workfront support.

Please note there is an ongoing defect for the missing month and day name from the Gantt chart in the task view.

and

 

. This is a known issue that our development team is currently investigating and working to resolve.

 

JamesWi7Author
Level 2
October 14, 2024

Thanks for sharing that!

Sven-iX
Community Advisor
Community Advisor
October 21, 2024

Per Support: 

 

Good morning! My development team has a fix for this issue that is expected to be released with this upcoming patch on Thursday. I will followup with you then to confirm that the issue is resolved.


@jameswi7  

@ambrna