Question
Frozen Project Percent Complete
Randomly a project's percent complete value will freeze and can't be updated until some clicks Project Actions > Recalculate Timeline. For example, we have a lot of projects where all of the tasks are at 100% complete and the project status is set to Complete, but the project's percent complete is showing at less than 100%. I can not find a reason for when it does or doesn't happen. This is happening with multiple users. Is anyone else having this issue? Some of the project settings: Completion mode = Automatic Summary completion mode = Automatic Update type = Automatic and On Change In the system settings we have the project setting "Estimate at Completion" set to "Calculate at project level"
Denver Lemont Cardinal Health
