Hi all, I need to create a filter for a task report to show all tasks with planned hours = 0. However, (task) planned hours does not seem to be available field for filtering the task report. Is there some workaround for this? Thanks!
Best answer by Srinija_N

"Planned Hours" is available only for the column(view), For Filter you can use "Task > Work".

 

Hope this helps!

 

Please mark my response as "correct reply" if this helped you and to help others. Thanks in advance!

1 reply

Srinija_N
Srinija_NAccepted solution
June 25, 2025

"Planned Hours" is available only for the column(view), For Filter you can use "Task > Work".

 

Hope this helps!

 

Please mark my response as "correct reply" if this helped you and to help others. Thanks in advance!

JenniferLegate
June 25, 2025

Thank you, @srinija_n. Exactly what I was looking for. Much appreciated.