Due dates to appear in Outlook

Avatar

Level 4

Forgive me if this has been asked before, I have found iterations of this question but they are linked to the previous community platform which our IT has blocked as being unsafe - judging by ensuing reactions to those posted on the older community platform, I need to see these suggestions!

Therefore, has anyone know or found a way in which due dates can appear in Outlook?

Thanks!

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

There is some information here about integrating the calendars between "home" and Outlook. 

 

https://experienceleague.adobe.com/docs/workfront/using/basics/home/use-home-area/configure-home-cal...

 

I would caution this because they are migrating away from the current "home" experience and moving to a new "home" so I'm not sure how long this will be a supported option.




View solution in original post

3 Replies

Avatar

Community Advisor

What action are you trying to do with the date date? Add a task or issue to a project? Submit a request? Is this for the standard outlook integration or do you have a custom outlook integration?




Avatar

Level 4

Hi Kellie - just to simply have the Workfront project completion due date appear in Outlook calendar. We have no Outlook integration at the moment, just learning about it, but this is something I know our teams would benefit from.

Thanks for responding

Avatar

Correct answer by
Community Advisor

There is some information here about integrating the calendars between "home" and Outlook. 

 

https://experienceleague.adobe.com/docs/workfront/using/basics/home/use-home-area/configure-home-cal...

 

I would caution this because they are migrating away from the current "home" experience and moving to a new "home" so I'm not sure how long this will be a supported option.