Tammie, We have a Project Manager Dashboard and one of the reports on there is a task report with these filters: Projecct > Owner ID, Equal, $$USER.ID Task > Planned Completion Date, Less Than Equal, $$TODAY+7D Assignment Roles > ID, Is Not Blank (so it doesn't pull in parent tasks) Project > Status, Equal, In Progress (so any projects still in planning or on hold don't pull in) Task > Percent Complete, Less Than, 100 (so it doesn't pull in completed tasks) OR all the above filters with a tweak to the percent complete one, plus: Task > Pending Approval, Equal, True Task > Percent Complete, Equal, 100