Expand my Community achievements bar.

SOLVED

Delaying a task start date

Avatar

Level 3

This may be a relatively easy solution but I'm relatively new to WF and it's stumping me at the moment.
I working on creating a template and I need to make a task start 5 days after the project is opened. This task doesn't have a predecessor so I can't  just +5d off a previous task. I just need it to start later than the other tasks in the project. Is there a simple way of doing this that I'm just over looking?

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Look at Predecessor Lag Types HERE. 

You can make it a start-start lag coming off a task with no predecessor (usually the first task).

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Look at Predecessor Lag Types HERE. 

You can make it a start-start lag coming off a task with no predecessor (usually the first task).