Is there a way to set a default planned completion date when a request is submitted rather than manually adjusting? For example, we have a certain type of request that we'd like the Planned Completion Date to be set to submission date + 3 days.
Any help is appreciated. Thank you!
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
In the queue details of your request queue, you can set a default duration for all of the requests that come in. If you set it to 3 all the requests planned completion dates will automatically calculate to be +3 days from the entry date of the request.
See here under 'Default Duration' a little more than halfway down the page: https://one.workfront.com/s/document-item?bundleId=the-new-workfront-experience&topicId=Content%2FMa...
In the queue details of your request queue, you can set a default duration for all of the requests that come in. If you set it to 3 all the requests planned completion dates will automatically calculate to be +3 days from the entry date of the request.
See here under 'Default Duration' a little more than halfway down the page: https://one.workfront.com/s/document-item?bundleId=the-new-workfront-experience&topicId=Content%2FMa...
Thank you SO much!! Exactly what I was looking for :)